Aftermath of the Mark VA
Nature Vol. 262 August 12 1976
525
11ature
August 12, 1976
Aftermath of the Mark VA
THE tale of the Jodrell Bank Mark VA radiotelescope
that was never built is a gloomy one from any point of
view. The Fifth Report from the Commons Committee
of Public Accounts (HMSO; £3.45) takes a look at it.
Original plans were for the Science Research Council
(SRC) to construct a 400-foot steerable dish (the Mark V);
the council sought approval from the Department of
Educatiion and Science (DES) in 1970 on the basis of an
estimate of £6.2 million (January 1970). A revision of the
cost to £8 million caused the SRC to propose a smaller
telescope~the Mark VA, with a 375-foot aperture,
which they hoped could be built within the £6.2 million
figure. A detailed desiign was to be prepared by the
consulting engineers Husband and Company (a firm well
experienced in radiotelescopes), covering drawings, bills
of quantities and an invitation to tender for construction.
The United Kingdom Atomic Energy Authority
(UKAEA) would act as project managers, and it was
estimated that £245,000 would be needed in consultants'
fees. A large fraction of this figure was tied to the final
tender price for construction.
Treasury approval for the design stage was given in
June 1971. Ten months later the consultants were given
the go-ahead to complete the design, if possible, within
twelve months. They were told to alert the UKAEA if it
seemed that the construction would cost more than was
originally planned (due allowance had been made for
inflation). Within six months they reported that the limit
had been reached. After that, however, they were under
no obl,igation to report costs further, and indeed had
declined to have any further reporting written into their
contract. The SRC's explanation for this was that "the
consulting engineer . . . was de,signing the telescope to
make it as cheap to build as he could. He was still
finding out how it could be built cheaply, and it was
more important for him to do that than to keep estimating
what the cost was".
The inevitable happened. In October 1973 the consultants finished; tenders received in March 1974,
reflecting the great uncertainties then prevailing in the
construction industry, were around the £14 million mark.
The total oost was put at £16 to £17 million. (It had been
estimated just before by the UKAEA that the £6.2
million~at 1970 prices__:_which was the original total
cost would have inflated to £10.7 million by January
1974.) Faced with a 50% growth in real terms in costs,
and having to live with negiigible overall growth, the
SRC abandoned the telescope in June 1974, having
learnt that total costs had risen even more in the interim
to £22 million.
But this left one matter outstanding~the consultants'
fee. As it was related to the tender price, it now amounted
to the sum of almost £600,000, although on this the
consultants eventually offered a rebate of £30,000. Even
so, the amount they received was rather more than
double what they must have expected on starting~a tidy
windfall even when inflation had taken its toll. The SRC,
which had not been informed itself of price escalation,
had in its turn not been able in 1973 to keep the DES
and the Treasury alerted to rising real costs, and had
to seek special Treasury authority for the total design
bill of £660,000.
It is fairly easy now to look back and see what went
wrong. People were unused to dealing with inflationary
conditiions, and so didn't exercise such stringent controls
as they would now. Even so, the telescope might have
come through unscathed were it not for the situation
which developed nationally during precisely the months
that potential contractors were preparing their tenders.
As it is the SRC gets a mild rap over the knuckles
for letting matters drift, and rightly so, although the
report has a rather optimistic view of the willingness of
the scientific community to drop major projects when
costs escalate. But what about the method by which the
consultants were paid?
H must be made clear that the issue here is in no
sense one of indulging in any gold-plating. The figures
mentioned and the evidence of the SRC and the DES all
fit in with the appalling way in which construction costs
escalated. Be that as it may, the taxpayer ended up
paying the consultants an "uncovenanted benefit", in the
words of the committee, totally unrelated to the cost of
the project. Wha,t is more, the SRC, having decided not
to go ahead. would have to pay an additional fee if it
chose to think again, as the plans are the copyright of
the consultants. The SRC did at the very outset enquire
about retaining the drawings, but was ,told that this
would roughly double the fees.
All of this is legal and common practice. Fees are
related to tender price, and copyright stays with the
designer. But i,t does seem to the outsider to be open
to charges of being inequitable, and it can lead to
cynicism. The Public Accounts Committee calls for
further consideration to be given to the way cons,ultancy
agreements work in the public sector. We hope someone
is doing just that.
0
© 1976 Nature Publishing Group
(...truncated)