Analysis and Mitigation of Shunt Capacitor Bank Switching Transients on 132 kV Grid Station, Qasimabad Hyderabad
Analysis and Mitigation of Shunt Capacitor Bank Switching
Transients on 132 kV Grid Station, Qasimabad Hyderabad
SUNNY KATYARA*, ASHFAQUE AHMED HASHMANI**, AND BHAWANI SHANKAR CHOWDHRY***
RECEIVED ON 1811.2014 ACCEPTED ON 17.03.2015
ABSTRACT
In this paper analysis and mitigation methods of capacitor bank switching transients on 132KV Grid
station, Qasimabad Hyderabad are simulated through the MATLAB software (Matrix Laboratory). Analysis
of transients with and without capacitor bank is made. Mathematical measurements of quantities such as
transient voltages and inrush currents for each case are discussed. Reasons for these transients, their
impact on utility and customer systems and their mitigation are provided.
Key Words: Capacitor Banks, Switching Transients, Capacitor Inrush Current, Pre-Insertion Resistor,
Current Limiting Reactor, Surge Arrestor, MATLAB.
1.
INTRODUCTION
I
n power system, transients have bad impact on its
reliability and may cause damage to or malfunctioning
of major equipments. The source of these transients
may be switching operations, lightning strikes or failure
of equipment. When shunt capacitor bank is to be switched
on live network, high frequency and high magnitude
transients may occur. Usually capacitor banks are installed
at feeder circuit to improve power factor and voltage
profile. Normally, these capacitor banks are not connected
all the time but switched on and off many times during the
day because the load on power system changing with
time according to certain load curves. These switching
actions will be accompanied by transient currents, when
a capacitor bank is closed on energized circuit [1].
Actually switching of capacitors produces more severe
transients as compared to energisation of load or cable
[2]. When an uncharged capacitor is switched on to
network, the system voltage will reduce, as it starts taking
energy from network instead of supplying. Hence severe
transients will take place when uncharged capacitor is being
switched on to network at peak voltage. The system voltage
will shoot up by the magnitude equal to the difference
between the system voltage and the voltage of capacitor
bank when a charged capacitor is switched on [3-4].
Theoretically, it has been observed that these transients
would lead to peak amplitude of 2 pu (per unit) but due to
inherent damping present in circuit, these transients are
limited below this value. The initial peak of transients
usually during sub-transient period is the most dangerous
one [5]. However effects of these transients are not
damaging enough to cause failure of line equipments, but
can act as catalyst to affect the most sensitive equipments
of the system and may produce un-necessary tripping of
equipments [6].
In this paper we are presenting Simulink analysis and
mitigation of capacitor switching transients on the
* Post-Graduate Student, ** Professor, and *** Meritorious Professor,
Institute of Information & Communication Technologies, Mehran University of Engineering & Technology, Jamshoro
Mehran University Research Journal of Engineering & Technology, Volume 34, No. 3, July, 2015 [ISSN 0254-7821]
291
Analysis and Mitigation of Shunt Capacitor Bank Switching Transients on 132 kV Grid Station, Qasimabad Hyderabad
distribution feeder connected to 40 MVA transformer at
132 kV grid station Qasimabad Hyderabad. Capacitor
banks are placed before feeder circuit and initially
energized at peak voltage of the circuit at grid station and
transients in current and voltage near the bank are
analyzed. Now in order to remove these transients different
mitigation techniques are to be adopted and there results
have been included too in this paper and finally comparison
is made on techniques that which is most efficient one.
2.
BASIC CONCEPT CONCERNING
ENERGIZATION OF CAPACITORS
Fig. 1 represents distribution network which provides
conceptual introduction about the capacitor switching
transients. R 1 and L 1 represent the resistance and
inductance of source. As shown in Fig. 1 capacitors C1
and C2 are fed by circuit breaker CB4. S1 and S2 represent
switches used to take in and out the capacitors C1 and C2.
Inductance of feeder between C1 and C2 is represented by
LB. Total impedance of feeder and distribution transformer
is represented by the combination of R2 and L2. Circuit
breaker CB3 is used here to interrupt the ground fault at
some distance on the feeder.
When switches S1 and S2 close at any instant to energize
capacitors, voltage at feeder to which CB4 is connected
collapses to the voltage on the capacitors and produce
oscillations. When these oscillations are damped out,
feeder voltage would return to its normal value again. But
if the capacitors are energized at peak value of voltage,
FIG. 1. NETWORK USED TO ILLUSTRATE CAPACITOR
SWITCHING TRANSIENTS
which is typically about 1.5-1.8 pu of phase to ground
voltage, large transients with frequency in range of 300800 Hz are produced initially. The frequency of these
transients is determined by source inductance L1 and
capacitance of capacitors connected [2].
Actually capacitors are connected in the form of three
phase large banks and breaker closes all three phases of a
capacitor bank simultaneously, so voltage at one of the
phase is always at peak [6-7].
3.
REDUCTION OF CAPACITOR
SWITCHINGTRANSIENTS
Many topologies and techniques are available to mitigate
transients such as; use of pre-insertion resistors, inrush
limiting reactors and surge arrester connected across the
capacitor bank. Each technique results in a different
manner to reduce the switching transients.
3.1
Current Limiting Reactors
Here reactor of suitable rating is used in series with the
capacitor bank. Due to use of this reactor the surge
impedance of the circuit increases and hence the peak of
inrush current is reduced. Since the inductor opposes the
change in current so current cannot change instantly,
therefore elevated frequency components of transient are
restricted and the effect of these inrush transients current
is condensed [2,7].
3.2
Pre-Insertion Resistors
In this method, switched resistors are used in series with
capacitor banks. Here the switch will introduce resistors
initially into network and then make contact with capacitor
bank. Due to the use of these resistors, overall losses in
the circuit are increased which facilitate to decrease the
peak value of transients in the voltage and current. The
time at which pre-insertion resistors are introduced into
circuit is about one fourth of supply frequency i.e. 50 Hz.
This helps to decrease the initial peak which is most
damaging one of transients [7].
Mehran University Research Journal of Engineering & Technology, Volume 34, No. 3, July, 2015 [ISSN 0254-7821]
292
Analysis and Mitigation of Shunt Capacitor Bank Switching Transients on 132 kV Grid Station, Qasimabad Hyderabad
3.3
Surge Arrester
Gap type surge arresters with a series non-linear resistor
can be used along with capacit (...truncated)